[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982367,712,1,"单选题","某工程双代号网络计划中，工作C有两项紧前工作A和B。工作A的最早开始时间为10，持续时间为5；工作B的最早开始时间为14，持续时间为4。则工作C的最早开始时间为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","15",{"key":22,"text":23,"correct":24},"D","18",true,"最早开始时间的计算规则如下：①若某工作只有一个紧前工作，则该工作的ES等于其紧前工作的EF；②若某工作为汇聚工作，即存在有多个紧前工作，则该工作的耶等于其所有紧前工作的EF中的最大值。题中，工作C的最早开始时间为：ES C =max[EF A ;EF B ]=max[10+5;14+4]=18。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]