[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982364":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982364,712,1,"单选题","决定WBS详细程度和层次多少的主要因素，主要是涉及项目参与者的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","责任能力和对项目的控制能力",true,{"key":16,"text":17,"correct":18},"B","筹资能力和对项目的控制能力",false,{"key":20,"text":21,"correct":18},"C","责任能力和对项目的熟悉程度",{"key":23,"text":24,"correct":18},"D","筹资能力和对项目的熟悉程度","决定WBS详细程度和层次多少的主要因素主要是涉及项目参与者的责任能力和对项目的控制能力。责任能力是指为完成项目工作任务而分配给每个小组或个人的责任和这些责任者的能力。控制能力是指在项目运行期间对项目的进度、成本以及质量等进行控制的能力。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]