[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982363,712,1,"单选题","在项目进度管理中，为具有合适的精细度和层级划分、可完整描述项目全部工作与进度的活动清单以及活动属性是()的成果。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定义活动",true,{"key":16,"text":17,"correct":18},"B","排列活动顺序",false,{"key":20,"text":21,"correct":18},"C","估算活动资源",{"key":23,"text":24,"correct":18},"D","制定进度计划","定义活动是指结合项目范围定义的可交付成果及其分解结构（一般为工作分解结构），确定为取得各项分解后可交付成果所需开展的各项具体工作（活动、作业和工序）。定义活动的成果为具有合适的精细度和层级划分、可完整描述项目全部工作与进度的活动清单以及活动属性。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]