[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982359,712,1,"单选题","项目成本管理可分为三个阶段性的工作，其目的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","保证项目质量",false,{"key":16,"text":17,"correct":18},"B","确定项目范围",true,{"key":20,"text":21,"correct":14},"C","降低项目风险",{"key":23,"text":24,"correct":14},"D","确保项目进度","将成本管理分为估算成本、编制成本预算、进行成本控制三个阶段性工作的目的是为了确定项目范围，根据可获得资金和管理政策及策略制定预算，确保项目在批准的预算范围内完成。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]