[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982357,712,1,"单选题","网络图中有()个时间参数。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","6",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","8","网络图中工作的6个时间参数为：①最早开始时间（ES）；②最早完成时间（EF）；③最迟开始时间（LS）；④最迟完成时间（LF）；⑤自由时差（FF）；⑥总时差(TF)。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]