[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982355,712,1,"单选题","双代号网络计划如图2-5所示（时间单位：天），其关键路径有()条。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","7","关键路径是总的工作持续时间最长的线路。本题中，该双代号网络计划的关键路线有6条，分别是：①一④一⑤一⑥一⑧一⑨一⑩(A→D→I→K)；①一④一⑤一⑥一⑧一⑩一⑩(A→D→I→M)；①一④一⑤一⑥一⑦一⑩一⑩(A→D→J→M)；④一②一③一④一⑤一⑥一⑧一⑨一⑩(C→D→I→K)；①一②一③一④一⑤一⑥一⑧一⑩一⑩(C→D→I→M)；①一②一③一④一⑤一⑥一⑦一⑩一⑩(C→D→J→M)；总工期为：T=3+5+4+3=15（天）。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]