[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982350,712,1,"单选题","工程网络计划执行过程中，如果某项工作实际进度拖延的时间超过其自由时差，则该工作()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必定影响其紧后工作的最早开始",true,{"key":16,"text":17,"correct":18},"B","必定变为关键工作",false,{"key":20,"text":21,"correct":18},"C","必定导致其后续工作的完成时间推迟",{"key":23,"text":24,"correct":18},"D","必定影响工程总工期","工作的自由时差（FF）是指在不影响其紧后工作最早开始的前提下，本工作可以利用的机动时间。如果某项工作实际进度拖延的时间超过其自由时差，则该工作将影响其紧后工作的最早开始时间。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]