[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982348":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982348,712,1,"单选题","下列关于挣值分析基本参数的说法错误的是()。 A、计划价值（PV），又称计划工作量预算费用 B、实际成本(A",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","的计算公式为、AC=已完成工作量*实际价格",false,{"key":16,"text":17,"correct":14},"B","实际成本(A",{"key":19,"text":20,"correct":14},"C","主要反映项目执行的实际消耗指标",{"key":22,"text":23,"correct":24},"D","挣值(EV)的计算公式为、EV=计划工作量*预算价格",true,"D项，挣值(EV)的计算公式为：EV=已完成工作量*预算价格。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]