[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982346,712,1,"单选题","费用绩效指数()时，表示实际费用高于预算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","大于1",false,{"key":16,"text":17,"correct":14},"B","等于1",{"key":19,"text":20,"correct":21},"C","小于1",true,{"key":23,"text":24,"correct":14},"D","大于","费用绩效指数CPI是指EV与AC之比，计算公式为：CPI=EV\u002FAC。当CPI＞1时，表示实际费用低于预算，项目处于节支状态。当CPI＜1时，表示实际费用高于预算，项目处于超支状态。当CPI=1时，表示实际费用等于预算费用。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]