[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982344,712,1,"单选题","在项目质量管理中，编制质量计划的主要依据不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目范围",false,{"key":16,"text":17,"correct":18},"B","项目费用计划",true,{"key":20,"text":21,"correct":14},"C","质量方案",{"key":23,"text":24,"correct":14},"D","技术标准和规划","编制质量计划的主要依据为项目范围、质量方案、技术标准和规范等，计划主要内容包括质量管理工作所涉及的组织结构、职责、程序、流程和所需资源，主要采用的工具包括成本效益分析、质量成本分析、标杆对照等工具。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]