[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982343,712,1,"单选题","成本控制系统以()为基础。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","范围衡量指标",false,{"key":16,"text":17,"correct":18},"B","绩效衡量指标",true,{"key":20,"text":21,"correct":14},"C","进度衡量指标",{"key":23,"text":24,"correct":14},"D","风险衡量指标","成本控制系统以绩效衡量指标（如作业活动或可交付成果的实际成本、实际现金流）为基础，每当发生项目范围变更、进度变化时，也要求对基本预算进行调整。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]