[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982341":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982341,712,1,"单选题","某工程网络计划中，工作H有两项紧后工作，最早完成时间分别为30和20，持续时间分别为10和8。若工作H的自由时差为零，则工作H的最早完成时间为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","12",true,{"key":20,"text":21,"correct":14},"C","24",{"key":23,"text":24,"correct":14},"D","30","最早完成时间(EF)是指某项活动能够完成的最早时间。题中，H工作的最早完成时间EF=min[30-10;20-8]=12。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]