[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982338,712,1,"单选题","下列各项中，不属于工作分解结构步骤的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定每个可交付成果的详细程度",false,{"key":16,"text":17,"correct":18},"B","估算分解持续时间",true,{"key":20,"text":21,"correct":14},"C","确定可交付成果的组成元素",{"key":23,"text":24,"correct":14},"D","核实分解的正确性","工作分解结构步骤为：①明确并识别出项目的各主要组成部分，即明确项目的主要可交付成果；②确定每个可交付成果的详细程度，以满足对其进行成本和时间估计的要求；③确定可交付成果的组成元素；④核实分解的正确性。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]