[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982337":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982337,712,1,"单选题","项目时间管理中，各工作过程会形成不同的成果，其中，项目网络图是()过程的成果。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作定义",false,{"key":16,"text":17,"correct":18},"B","工作排序",true,{"key":20,"text":21,"correct":14},"C","工作时间估计",{"key":23,"text":24,"correct":14},"D","工作分解","工作排序的主要成果是表达项目各工作间逻辑关系的项目网络图。项目网络图按其绘制方式不同，可以分为单代号网络图和双代号网络图两种主要方式。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]