[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982336":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982336,712,1,"单选题","在项目时间管理中，需要确定项目各项工作的开始时间和结束时间的工作过程是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","排列活动顺序",false,{"key":16,"text":17,"correct":14},"B","估算活动资源",{"key":19,"text":20,"correct":21},"C","制订进度计划",true,{"key":23,"text":24,"correct":14},"D","控制进度","制订进度计划是分析活动顺序、持续时间、资源需求和进度约束，编制项目进度计划的过程。编制项目进度计划需要确定项目各项工作的开始和结束时间。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]