[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982334,712,1,"单选题","对每项作业活动将发生的成本进行估计，结合作业活动清单和进度计划的安排，又可以进行()的预测和统计分析。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作量",false,{"key":16,"text":17,"correct":14},"B","实际成本",{"key":19,"text":20,"correct":14},"C","项目采购",{"key":22,"text":23,"correct":24},"D","现金流",true,"对每项作业活动将发生的成本进行估计，结合作业活动清单和进度计划的安排，又可以进行现金流的预测和统计分析。为了应对未来的不确定事件的发生，可以增加一部分资源配置用于管理储备，所得到的预算就成为项目成本控制的基准。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]