[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982333,712,1,"单选题","项目管理的中心任务是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目整合管理",false,{"key":16,"text":17,"correct":14},"B","项目质量管理",{"key":19,"text":20,"correct":14},"C","项目风险管理",{"key":22,"text":23,"correct":24},"D","项目进度管理",true,"项目时间管理（又称为“项目进度管理”），是指为确保项目按期完成对所有必须完成的工作而进行的管理。项目能否按期完成往往关系重大，项目时间管理既是项目管理的中心任务，也是项目目标体系中三大目标之一。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]