[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982332,712,1,"单选题","进度绩效指数SPI＞1时，()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","表示实际进度比计划进度快，进度提前",true,{"key":16,"text":17,"correct":18},"B","表示实际进度比计划进度慢，进度延期",false,{"key":20,"text":21,"correct":18},"C","表示实际进度等于计划进度",{"key":23,"text":24,"correct":18},"D","无法比较实际进度与计划进度","进度绩效指数，SPI是指EV与PV之比，计算公式为：SPI=EV\u002FPV。当SPI＞1时，表示实际进度比计划进度快，进度提前。当，SPI＜1时，表示实际进度比计划进度慢，进度延期。当SPI=1时，表示实际进度等于计划进度。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]