[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982331,712,1,"单选题","关于网络图绘制的基本规则，下列说法不正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","网络图的流向一般是从左向右",false,{"key":16,"text":17,"correct":14},"B","节点代表事件",{"key":19,"text":20,"correct":14},"C","一项工作必须等到与它相连的所有紧前工作结束后才能开始",{"key":22,"text":23,"correct":24},"D","网络图中可以出现循环回路",true,"网络图的绘制既要正确表达已经确定的工作之间的逻辑关系，又要遵从一定的绘图规则。网络图绘制的基本规则如下：①网络图的流向一般是从左向右；②节点代表事件，即工作的开始或结束，一般情况下网络图中只有一个起点节点和一个终点节点；③箭线代表工作，不允许出现双向箭头或无箭头的连线；④一项工作必须等到与它相连的所有紧前工作结束后才能开始；⑤网络图中不允许出现循环回路。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]