[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982329,712,1,"单选题","双代号网路计划中的关键路径是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总时差为零的路径",false,{"key":16,"text":17,"correct":14},"B","总的工作持续时间最短的路径",{"key":19,"text":20,"correct":14},"C","一经确定，不会发生转移的路径",{"key":22,"text":23,"correct":24},"D","持续时间最长的路径",true,"网络图中从起点节点到终点节点的各条路径中，持续时间最长的路径称为关键路径。关键路径上的工作称为关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]