[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982320":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982320,712,1,"单选题","关于项目利益相关方的特点，下列说法错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不同利益相关方在项目中的责任和职权各不相同，并且随项目生命周期的进展而变化",false,{"key":16,"text":17,"correct":14},"B","利益相关方的识别过程是一个持续的过程，一次性完全识别有一定的难度",{"key":19,"text":20,"correct":14},"C","利益相关方对项目的利益诉求可能是冲突的",{"key":22,"text":23,"correct":24},"D","利益相关方对项目的影响是负面的",true,"D项，利益相关方对项目的影响有正面的也有负面的。某些利益相关方预期从一个成功的项目得益，而另一类利益相关方则可能看到项目成功给他们带来的负面影响。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]