[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982319":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982319,712,1,"单选题","项目质量管理过程中，编制质量计划的主要目的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析和判断影响质量的主次关系",false,{"key":16,"text":17,"correct":18},"B","确定项目应达到的质量标准",true,{"key":20,"text":21,"correct":14},"C","建立质量缺陷的应急响应体系",{"key":23,"text":24,"correct":14},"D","组建项目策划团队","编制质量计划旨在识别项目及其产品的质量要求和／或标准，并书面描述项目将如何达到这些要求和／或标准的过程。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]