[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982317,712,1,"单选题","已知某起点节点引出的工作的持续时间为4天，其最早开始时间为第18天，最迟开始时间为第21天，则该工作的最早完成时间为第()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","18",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":21},"C","22",true,{"key":23,"text":24,"correct":14},"D","25","该工作最早完成时间(EF)=最早开始时间（ES）+持续时间(D)。第18天开始，经历四天时间是第22天即为最早完成时间。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]