[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982313":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982313,710,2,"多选题","招标采购合同管理的阶段主要包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同规划",true,{"key":16,"text":17,"correct":18},"B","合同审批",false,{"key":20,"text":21,"correct":14},"C","招标采购",{"key":23,"text":24,"correct":14},"D","合同签订",{"key":26,"text":27,"correct":14},"E","合同履行","ACDE","招标采购合同管理的生命期和整个项目建设期有关，主要包括合同规划、招标采购、合同签订和合同履行等阶段，这几个阶段既相对独立存在，具有各自不同的内容和特点，同时各个阶段之间又密切联系，不可分割，共同构成一个完整的管理过程。B项，不属于招标采购合同管理的阶段。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]