[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982309":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982309,710,2,"多选题","下列各项中，属于主动控制措施的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","识别风险和风险管理",true,{"key":16,"text":17,"correct":14},"B","详细调查并分析外部环境条件",{"key":19,"text":20,"correct":21},"C","建立控制组织、明确控制责任，检查发现情况及时处理",false,{"key":23,"text":24,"correct":14},"D","制定必要的应急备用方案",{"key":26,"text":27,"correct":21},"E","建立有效的信息反馈系统","ABD","主动控制就是预先分析目标偏离的可能性，并拟订和采取各项预防性措施，以保证计划目标得以实现。主动控制措施包括：①详细调查并分析外部环境条件；②识别风险和风险管理；③科学制定计划，做好计划可行性分析；④高质量地做好组织工作，使组织与目标和计划高度一致；⑤制定必要的应急备用方案；⑥加强信息收集、整理和研究工作，为预测招标采购项目的未来发展提供全面、及时、可靠的信息。CE两项属于被动控制措施。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]