[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982298":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982298,710,2,"多选题","合同履行阶段的合同分析可分为()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同总体分析",true,{"key":16,"text":17,"correct":18},"B","合同风险分析",false,{"key":20,"text":21,"correct":14},"C","合同工作分析",{"key":23,"text":24,"correct":14},"D","合同交底",{"key":26,"text":27,"correct":18},"E","合同责任分析","ACD","合同履行阶段的合同分析可分为：①合同总体分析，其主要对象是合同的全部内容；②合同工作分析，是在合同总体分析的基础上，依据合同协议书、合同条件、规范、图纸、工作量表等，确定各级管理人员的合同工作，以及划分各责任人的合同责任；③合同交底，指合同管理人员在对合同主要内容作出解释和说明的基础上，通过组织项目管理人员学习合同条文和合同总体分析结果，使大家熟悉合同中的主要内容、各种规定、管理程序，熟悉合同风险、合同责任和工程范围、各种行为的法律后果等，使全体人员都树立全局观念，工作协调一致，避免执行中的违约行为。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]