[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982269":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982269,710,2,"多选题","下列各项中，针对于已建成的基础设施项目的特许经营合同模式有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","BOT",false,{"key":16,"text":17,"correct":14},"B","BOO",{"key":19,"text":20,"correct":21},"C","POT",true,{"key":23,"text":24,"correct":21},"D","ROT",{"key":26,"text":27,"correct":21},"E","TOT","CDE","A项，BOT模式，即“建设一经营一转让”模式；B项，BOO模式，即“建设一拥有一运营”模式；C项，POT模式，即“购买一经营一移交”模式；D项，ROT模式，即“重整一经营一移交”模式；E项，TOT模式，即“转让一经营一转让”模式。CDE三项未涉及项目的建设，属于针对已建成的基础设施项目的特许经营合同模式。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]