[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982221":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982221,710,2,"多选题","下列关于设计咨询合同与设计合同的表述中，正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计咨询合同的工作成果是设计文件",false,{"key":16,"text":17,"correct":14},"B","设计合同是对设计成果的评价和优化",{"key":19,"text":20,"correct":21},"C","设计合同的签订与执行须严格按照《建设工程勘察设计管理条例》等规定",true,{"key":23,"text":24,"correct":21},"D","设计咨询合同一般不需要设计咨询单位达到法定资质要求",{"key":26,"text":27,"correct":14},"E","设计咨询合同与设计合同没有区别","CD","AB两项，设计合同的工作成果是设计文件，而设计咨询合同是对设计成果的评价和优化；CDE三项，设计合同的签订与执行须严格按照《建设工程勘察设计管理条例》、《工程建设项目勘察设计招标投标办法》、《建筑工程设计招标投标管理办法》、《建设工程勘察设计资质管理规定》等规定，而设计咨询合同一般不需要设计咨询单位达到法定资质要求。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]