[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982204":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982204,710,2,"多选题","下列关于项目前期咨询服务收费条款的表述中，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","收费标准由工程咨询机构与委托人协商确定",true,{"key":16,"text":17,"correct":18},"B","工程咨询收费标准是强制性的，不允许当事人约定",false,{"key":20,"text":21,"correct":14},"C","咨询成果通常由工程咨询单位负责完善",{"key":23,"text":24,"correct":14},"D","工程咨询单位对咨询成果进行完善的，委托人无需另支付咨询费用",{"key":26,"text":27,"correct":14},"E","工程咨询机构与委托人可以约定当工程咨询单位所提交的咨询成果达不到合同规定标准时的相关安排","ACDE","项目前期咨询服务收费条款的内容包括：工程咨询收费标准由工程咨询机构与委托人协商确定；同时双方可以约定当工程咨询单位所提交的咨询成果达不到合同规定标准时的相关安排，即通常由工程咨询单位负责完善咨询成果，但委托人不另支付咨询费用。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]