[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982202":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982202,710,2,"多选题","下列关于工程造价咨询合同管理要点的说法中，正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对时效性较强的市场价格一般应当通过询价等方式获得第一手直接信息",true,{"key":16,"text":17,"correct":14},"B","委托人和造价咨询企业应当在合同中明确各阶段造价咨询企业提供服务的具体方式",{"key":19,"text":20,"correct":21},"C","相关造价文件初稿编制完成后经过审核即可形成最终造价成果文件",false,{"key":23,"text":24,"correct":21},"D","对工程造价文件进行有效的档案管理仅对委托人有意义",{"key":26,"text":27,"correct":14},"E","执业规范管理应当建立健全从业人员的监督制约机制","ABE","C项，造价成果性文件直接体现造价咨询企业的服务水平，影响合同目标的实现，因此委托人和造价咨询企业应重点关注造价成果性文件的质量管理。相关造价文件初稿编制完成后一般要经过审核与审定两道程序才能形成最终造价成果文件。D项，对工程造价文件进行有效的档案管理，不仅可以还原造价咨询合同实际履行情况，使各项造价成果文件有据可循，而且档案文件还可以作为委托人和承包人进行结算和处理造价争议的重要依据。所以无论对于委托人还是造价咨询人而言，该项管理活动均具有十分重要的意义。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]