[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982126":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982126,710,2,"多选题","在常用价格术语的责任、风险、费用对比中，属于买方办理其保险的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","FOB",true,{"key":16,"text":17,"correct":18},"B","CIF",false,{"key":20,"text":21,"correct":18},"C","CIP",{"key":23,"text":24,"correct":18},"D","DDP",{"key":26,"text":27,"correct":14},"E","CFR","AE","BCD三项都是由卖方负责办理保险。《2010通则》包含11种术语，按不同类别分为E、F、C、D四个组。E组只包括一种贸易术语——EXW，这是在商品产地交货的贸易术语。F组包含有FCA、FAS和FOB三种术语，按这些术语成交，卖方须将货物交给买方指定的承运人，从交货地至目的地的运费由买方负担。C组包括CFR、CIF、CPT、CIP四种术语，采用这些术语时，卖方要订立运输合同，但不承担从装运地启运后所发生的货物损坏或灭失的风险及额外费用。D组包括DAT、DAP和DDP三种术语，按照这些术语达成交易，卖方必须负担将货物运往指定的进口国交货地点的一切风险、责任和费用。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]