[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982095":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982095,710,2,"多选题","工程总承包是对工程项目的()等实行全过程或若干阶段的承包。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","勘察",true,{"key":16,"text":17,"correct":14},"B","设计",{"key":19,"text":20,"correct":14},"C","采购",{"key":22,"text":23,"correct":14},"D","施工",{"key":25,"text":26,"correct":27},"E","运行与维护",false,"ABCD","工程总承包是指从事工程总承包的企业受发包人委托，按照合同约定对工程项目的勘察、设计、采购、施工、试运行（竣工验收）等实行全过程或若干阶段的承包。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]