[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982092":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982092,710,2,"多选题","下列属于设计进度主要控制点的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计各专业间的条件关系及其进度",true,{"key":16,"text":17,"correct":14},"B","初步设计完成和提交时间",{"key":19,"text":20,"correct":21},"C","设计技术方案的评审",false,{"key":23,"text":24,"correct":14},"D","关键设备和材料请购文件的提交时间",{"key":26,"text":27,"correct":14},"E","进度关键线路上的设计文件提交时间","ABDE","设计进度主要控制点一般应包括：①设计各专业间的条件关系及其进度；②初步设计完成和提交时间；③关键设备和材料请购文件的提交时间；④进度关键线路上的设计文件提交时间；⑤施工图设计完成和提交时间；⑥设计工作结束时间。C项属于设计质量控制点。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]