[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982091":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982091,710,2,"多选题","在勘察合同中，通常首先要对所委托勘察的工程基本情况和勘察任务进行说明，其主要内容包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设工程项目的名称",true,{"key":16,"text":17,"correct":14},"B","工程地点",{"key":19,"text":20,"correct":14},"C","工程规模、特征",{"key":22,"text":23,"correct":24},"D","工期",false,{"key":26,"text":27,"correct":14},"E","勘察任务与技术要求","ABCE","在勘察合同中，通常首先要对所委托勘察的工程基本情况和勘察任务进行说明，主要内容如下：①工程名称；②工程地点；③工程立项批准文件号、日期；④工程勘察任务委托文号、日期；⑤工程规模、特征；⑥工程勘察任务与技术要求；⑦承接方式；⑧预计的勘察工作量。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]