[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982087":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982087,710,2,"多选题","在勘察设计合同变更管理中需要注意()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","应尽快提出变更要求或指令",true,{"key":16,"text":17,"correct":14},"B","应尽快下达变更要求或指令",{"key":19,"text":20,"correct":14},"C","应迅速而全面地落实和执行变更指令",{"key":22,"text":23,"correct":14},"D","应严格遵守变更程序",{"key":25,"text":26,"correct":27},"E","为尽快下达变更指令，当事人双方可以不签署变更协议",false,"ABCD","在合同变更管理中要注意以下几个方面：①应尽快提出或下达变更要求或指令。因为时间拖得越长，造成的损失越多，双方的争执越大。②应迅速而全面地落实和执行变更指令。对于勘察人（设计人）来说，迅速地执行发包人的变更指令，调整工作部署，可以减少费用和时间的浪费。这种浪费往往被认为是勘察人（设计人）管理失误造成的，难以得到补偿。③应严格遵守变更程序。即变更指令应以书面形式下达，如果是口头指令，勘察人（设计人）应在指令执行后立即得到发包人的书面认可。E项，若非紧急情况，双方应首先签署变更协议，对变更的内容、变更后的费用与工期的补偿达成一致意见后，再下达变更指令。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]