[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982081":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982081,710,2,"多选题","下列关于设计文件与协调的说法中，正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","民用建筑工程设计一般分为方案设计、初步设计和施工图设计三个阶段",true,{"key":16,"text":17,"correct":14},"B","初步设计文件应当满足编制施工招标文件、主要设备材料订货和编制施工图设计文件的需要，是下一阶段施工图设计的基础",{"key":19,"text":20,"correct":21},"C","除合同另有约定外，自监理人收到承包人的设计文件以及承包人的通知之日起，发包人对承包人的设计文件审查期不超过20天",false,{"key":23,"text":24,"correct":21},"D","承包人的设计文件不需要报发包人审查同意",{"key":26,"text":27,"correct":14},"E","承包人应按照发包人要求，在合同进度计划中专门列出设计进度计划，报发包人批准后执行。承包人需按照经批准后的计划开展设计工作","ABE","C项，审查的范围和内容在发包人要求中约定。除合同另有约定外，自监理人收到承包人的设计文件以及承包人的通知之日起，发包人对承包人的设计文件审查期不超过21天；D项，承包人的设计文件应报发包人审查同意。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]