[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982067":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982067,710,2,"多选题","勘察设计过程中的合同管理主要包括()等方面。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目审批",false,{"key":16,"text":17,"correct":18},"B","合同资料文档管理",true,{"key":20,"text":21,"correct":18},"C","设计进度管理",{"key":23,"text":24,"correct":18},"D","合同实施的跟踪与监督",{"key":26,"text":27,"correct":18},"E","合同变更管理","BCDE","勘察设计过程合同管理主要包括以下方面：①合同资料文档管理；②设计进度管理；③合同实施的跟踪与监督；④合同变更管理。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]