[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982062":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982062,710,2,"多选题","关于合同价格与支付，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","除专用合同条款另有约定外，合同价格包括签约合同价以及按照合同约定进行的调整",true,{"key":16,"text":17,"correct":18},"B","工程进度付款只能按月支付",false,{"key":20,"text":21,"correct":14},"C","监理人应从发包人的每笔进度付款中，按专用合同条款的约定扣留质量保证金，直至扣留的质量保证金总额达到专用合同条款约定的金额或比例为止",{"key":23,"text":24,"correct":14},"D","预付款用于承包人为合同工程的设计和工程实施购置材料、工程设备、施工设备、修建临时设施以及组织施工队伍进场等",{"key":26,"text":27,"correct":14},"E","最终结清条款包括最终结清申请单、最终结清证书和支付时间","ACDE","B项，工程进度付款条款包括付款时间、支付分解表、进度付款申请单、进度付款证书和支付时间、工程进度付款的修正等方面。其中，关于付款时间，工程进度付款按月支付，也可以根据工程项目的里程碑事件确定。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]