[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982061":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982061,710,2,"多选题","下列属于方案设计阶段的工作内容的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对建设项目进行总体部署和安排",true,{"key":16,"text":17,"correct":18},"B","对批准的可行性研究报告的深化",false,{"key":20,"text":21,"correct":14},"C","细化功能分区",{"key":23,"text":24,"correct":14},"D","细化总平面布局",{"key":26,"text":27,"correct":14},"E","细化各项技术经济指标","ACDE","方案设计阶段的工作内容包括：①按照批准的立项文件要求，对建设项目进行总体部署和安排，使设计构思和设计意图具体化；②细化总平面布局、功能分区、总体布置、空间组合、交通组织等；③细化总用地面积、总建筑面积等各项技术经济指标。方案设计的内容与深度应当满足编制初步设计和项目投资估算的需要。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]