[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982055":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982055,710,2,"多选题","下列关于任命发包人代表的说法中，正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人应在通用合同条款中明确其负责工程设计的发包人代表",false,{"key":16,"text":17,"correct":14},"B","发包人代表在授权范围内的行为与发包人承担连带责任",{"key":19,"text":20,"correct":14},"C","发包人代表在授权范围外的行为由发包人承担法律责任",{"key":22,"text":23,"correct":24},"D","发包人更换发包人代表的，应在专用合同条款约定的期限内提前书面通知设计人",true,{"key":26,"text":27,"correct":24},"E","发包人代表不能按照合同约定履行义务，设计人可以要求发包人撤换发包人代表","DE","发包人应在专用合同条款中明确其负责工程设计的发包人代表的姓名、职务、联系方式及授权范围等事项。发包人代表在发包人的授权范围内，负责处理合同履行过程中与发包人有关的具体事宜。发包人代表在授权范围内的行为由发包人承担法律责任。发包人更换发包人代表的，应在专用合同条款约定的期限内提前书面通知设计人。发包人代表不能按照合同约定履行其职责及义务，并导致合同无法继续正常履行的，设计人可以要求发包人撤换发包人代表。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]