[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982053":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982053,710,2,"多选题","下列属于进度付款申请单的内容的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","当期应支付金额总额",true,{"key":16,"text":17,"correct":14},"B","当期根据支付分解表应支付金额，以及截至当期期末累计应支付金额",{"key":19,"text":20,"correct":21},"C","技术服务培训费",false,{"key":23,"text":24,"correct":21},"D","材料和工程设备费",{"key":26,"text":27,"correct":14},"E","当期根据合同应增加和扣减的其他金额，以及截至当期期末累计增加和扣减的金额","ABE","ABE三项，通常情况下，进度付款申请单应包括下列内容：①当期应支付金额总额，以及截至当期期末累计应支付金额总额、已支付的进度付款金额总额；②当期根据支付分解表应支付金额，以及截至当期期末累计应支付金额；③当期根据合同价格约定计量的已实施工程应支付金额，以及截至当期期末累计应支付金额；④当期根据变更条款应增加和扣减的变更金额，以及截至当期期末累计变更金额；⑤当期根据索赔条款应增加和扣减的索赔金额，以及截至当期期末累计索赔金额；⑥当期根据预付款条款约定应支付的预付款和扣减的返还预付款金额，以及截至当期期末累计返还预付款金额；⑦当期根据合同约定应扣减的质量保证金金额，以及截至当期期末累计扣减的质量保证金金额；⑧当期根据合同应增加和扣减的其他金额，以及截至当期期末累计增加和扣减的金额。CD两项属于支付分解表的内容。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]