[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982048":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982048,710,2,"多选题","计量是确定施工合同价格和支付合同价款的基础和依据，规范计量活动主要从()等方面予以明确。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","明确工程量计量规则",true,{"key":16,"text":17,"correct":18},"B","工程进度",false,{"key":20,"text":21,"correct":14},"C","计量周期",{"key":23,"text":24,"correct":18},"D","工程质量",{"key":26,"text":27,"correct":14},"E","计量的具体程序和具体内容","ACE","计量与支付条款是建设工程施工合同重点条款之一，其中，计量是确定施工合同价格和支付合同价款的基础和依据，也是施工合同履行中经常出现争议的活动，规范计量活动主要从计量规则、计量周期和计量程序等三个方面予以明确。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]