[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982043":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982043,710,2,"多选题","关于施工专业分包合同的变更管理和索赔管理，下列说法正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","专业分包人收到总承包人发出的变更指令或经总承包人确认的发包人变更指令后，方可实施变更。未经许可，专业分包人不得擅自对工程的任何部分进行变更",true,{"key":16,"text":17,"correct":14},"B","施工专业分包合同的变更管理主要围绕变更的及时性、变更引起的费用和工期展开",{"key":19,"text":20,"correct":21},"C","专业分包人认为有权得到追加付款和（或）延长工期的，应在知道或应当知道索赔事件发生后15天内，向总承包人递交索赔意向通知书，并说明发生索赔事件的事由",false,{"key":23,"text":24,"correct":14},"D","总承包人认为专业分包人索赔请求合理的，且应由发包人承担赔付责任的，总承包人应及时履行施工总承包合同中的索赔义务",{"key":26,"text":27,"correct":14},"E","专业分包的索赔流程设置应当与总承包人向专业发包人的索赔流程予以匹配，否则总承包合同和施工专业分包合同的履行均受到影响，并导致合同履行的困难","ABDE","C项，专业分包人认为有权得到追加付款和（或）延长工期的，应在知道或应当知道索赔事件发生后14天内，向总承包人递交索赔意向通知书，并说明发生索赔事件的事由，在发出索赔意向通知书后14天内，向总承包人正式递交索赔报告，索赔事件影响结束后14天内，专业分包人应向总承包人递交最终索赔报告，总承包人应在收到索赔报告后14天内完成审查等。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]