[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982042":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982042,710,2,"多选题","下列关于发包人和勘察人的合同责任的说法中，正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人提供有关资料、文件超过规定期限15天以内，勘察人按合同规定交付报告、成果、文件的时间顺延",true,{"key":16,"text":17,"correct":14},"B","发包人提供有关资料、文件超过规定期限15天以上时，勘察人有权重新确定交付报告、成果、文件的时间",{"key":19,"text":20,"correct":14},"C","勘察过程中的任何变更，经办理正式变更手续后，发包人应按实际发生的工作量支付勘察费",{"key":22,"text":23,"correct":24},"D","发包人不按时支付勘察费或进度款，勘察人在约定支付时间15天后，向发包人发出书面催款的通知",false,{"key":26,"text":27,"correct":14},"E","由于工程停建而终止合同，勘察人完成的工作量超过50%时，发包人应支付勘察人勘察费用的100%","ABCE","D项，发包人不按时支付勘察费或进度款，勘察人在约定支付时间10天后，向发包人发出书面催款的通知，发包人收到通知后仍不按要求付款，勘察人有权停工，因此导致工期顺延的，发包人还应承担滞纳金。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]