[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982041":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982041,710,2,"多选题","下列关于设计计划编制的说法中，正确的有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计计划应在项目初始阶段由设计经理负责组织编制，经承包人有关职能部门评审后，由项目经理批准实施",true,{"key":16,"text":17,"correct":14},"B","设计进度计划应符合项目总进度计划的要求",{"key":19,"text":20,"correct":14},"C","设计计划应满足合同约定的质量目标与要求以及相关的质量规定和标准",{"key":22,"text":23,"correct":14},"D","承包人需按照经批准后的计划开展设计工作",{"key":25,"text":26,"correct":27},"E","承包人应按照监理人要求，在合同进度计划中专门列出设计进度计划，报发包人批准后执行",false,"ABCD","设计计划应在项目初始阶段由设计经理负责组织编制，经承包人有关职能部门评审后，由项目经理批准实施。设计计划应满足合同约定的质量目标与要求以及相关的质量规定和标准。设计进度计划应符合项目总进度计划的要求，并应充分考虑与工程勘察、采购、施工、试运行的进度协调，还应考虑设计工作的内部逻辑关系及资源分配、外部约束条件等。承包人需按照经批准后的计划开展设计工作。E项，承包人应按照发包人要求，在合同进度计划中专门列出设计进度计划，报发包人批准后执行。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]