[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982038":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982038,710,2,"多选题","关于变更程序，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","变更程序按照提出变更、变更估价、变更指示执行",true,{"key":16,"text":17,"correct":18},"B","变更指示并非只能由监理人发出",false,{"key":20,"text":21,"correct":14},"C","监理人应按照合同约定和合同当事人商定或确定变更价格",{"key":23,"text":24,"correct":14},"D","承包人收到监理人按合同约定发出的文件，经检查认为其中存在对发包人要求变更情形的，可向监理人提出书面变更建议",{"key":26,"text":27,"correct":14},"E","承包人收到监理人的变更意向书后认为难以实施此项变更的，应立即通知监理人，说明原因并附详细依据","ACDE","变更按照以下程序执行：①变更的提出。具体包括：a.在合同履行过程中，监理人可向承包人发出变更意向书；b.承包人收到监理人按合同约定发出的文件，经检查认为其中存在对发包人要求变更情形的，可向监理人提出书面变更建议；c.承包人收到监理人的变更意向书后认为难以实施此项变更的，应立即通知监理人，说明原因并附详细依据。②变更估价。监理人应按照合同约定和合同当事人商定或确定变更价格。③变更指示。变更指示只能由监理人发出。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]