[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982034":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982034,710,2,"多选题","通常而言，发包人在与承包人签订建设工程施工合同前应确保完成的事项包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程项目的整体设计已经批准",false,{"key":16,"text":17,"correct":18},"B","工程项目已经列入年度建设计划",true,{"key":20,"text":21,"correct":18},"C","有能够满足施工需要的设计文件和有关技术资料",{"key":23,"text":24,"correct":18},"D","建设资金和主要建筑材料设备来源已经落实",{"key":26,"text":27,"correct":18},"E","招标发包工程，已经完成招投标程序且已经确定中标人。","BCDE","通常而言，发包人在与承包人签订建设工程施工合同前应确保完成以下事项：①工程项目的初步设计已经批准；②工程项目已经列入年度建设计划；③有能够满足施工需要的设计文件和有关技术资料；④建设资金和主要建筑材料设备来源已经落实；⑤招标发包工程，已经完成招投标程序且已经确定中标人。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]