[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982033":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982033,710,2,"多选题","根据索赔发生的原因不同，可将其分为()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同一方违约引发的索赔",true,{"key":16,"text":17,"correct":14},"B","合同文件错误",{"key":19,"text":20,"correct":21},"C","政策规定",false,{"key":23,"text":24,"correct":14},"D","施工外部环境变化",{"key":26,"text":27,"correct":14},"E","其他原因引起的索赔","ABDE","无论是发包人索赔还是承包人索赔，均必须具有合理理由方可得到支持。工程建设项目本身特点是投资大、工期长，参与者多，且所处环境有许多不确定性，因此索赔经常发生，且数额很大。归纳起来，根据索赔发生的原因不同，具体可分如下几种情况：①合同一方违约引发的索赔；②合同文件错误；③施工外部环境变化；④其他原因引起的索赔。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]