[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982032":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982032,710,2,"多选题","关于工期条款，下列说法正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同当事人在签订工期条款时，首先，应当明确约定开工日期和竣工日期，而且要载明具体的工期总日历天数",true,{"key":16,"text":17,"correct":14},"B","为了充分保障合同当事人的工期利益，标准文件同时规定合同当事人可以在专用合同条款中增列因发包人原因导致工期延误的情形",{"key":19,"text":20,"correct":21},"C","工程实践中，实际开工日期和实际竣工日期往往与计划开竣工日期往往是一致的",false,{"key":23,"text":24,"correct":14},"D","因发包人原因导致工期延误的，工期可以顺延，发包人还可能需要向承包人支付因工期延误给其增加的费用，且发包人应支付承包人合理的利润",{"key":26,"text":27,"correct":14},"E","为避免出现合同履行中工期延误产生的不利局面，发包人应在施工合同中明确约定逾期竣工的违约金计算方法","ABDE","C项，工程实践中，实际开工日期和实际竣工日期往往与计划开竣工日期不同，此时需要根据实际开工日期、实际竣工日期以及工期总日历天数、工期是否存在顺延等因素判断承包人是否存在延误工期的事实以及工期延误的具体天数。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]