[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982030":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982030,710,2,"多选题","下列关于提交资料和提交的勘察成果的说法中，正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人应及时向勘察人提供相关的文件资料，并对其准确性、可靠性负责",true,{"key":16,"text":17,"correct":14},"B","发包人应向勘察人提供工程批准文件和勘察许可等批件（复印件）",{"key":19,"text":20,"correct":14},"C","勘察人应按时向发包人提交勘察成果资料并对其质量负责",{"key":22,"text":23,"correct":24},"D","适用《建设工程勘察合同示范文本（一）》的勘察活动需要分批提供成果资料文件",false,{"key":26,"text":27,"correct":24},"E","适用《建设工程勘察合同示范文本（一）》的勘察活动需要提交四份勘察成果资料","ABC","DE两项，适用《建设工程勘察合同示范文本（一）》的勘察活动一般在勘察任务结束时，提交四份勘察成果资料，而适用《建设工程勘察合同示范文本（二）》的勘察活动则可能需要分批提供报告、成果资料或相应的文件。在合同中要注明勘察成果资料的名称、需要的份数、对内容的详细要求及应提交的时间。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]